Yinmin Copper Mine, Jinsha Mining, Yunnan Copper Group

Time of publication:2026-01-27


Project type:


EPC general contracting of the paste lining system with full tails



Project description:


Productivity of the system is 100 m³/h. The pulp is condensed in a deep cone condenser to 73%, mixed with cement and transported to a distance of up to 2000 m.


Project results:


After the implementation of the project, the dumping of tails in the tail storage was stopped. The deposition of underground voids allows to extract entire ore, increasing the extraction rate. The solid content in the plum is below 200 ppm, the water is returned to the circulating cycle of the enrichment plant.